Updated 2026-11-25 ยท 4 min read
What does UKRA ask you to send?
UKRA's Level 3 Procedure page (read 25 November 2026, no update date shown) says the flyer should send a detailed report to the project advisor two months before the intended launch. It lists six items:
- A completely filled out Pre-Flight Data Capture form.
- Drawings showing airframe components, fins, bulkheads, internal structures, adhesive joints, recovery parts and payloads.
- A parts list with material descriptions, adhesive types, screw sizes and gauges, and material thicknesses.
- A detailed motor assembly diagram showing retainers, locators and the placement of related systems.
- Schematics of recovery system electronics, including batteries, circuit designs and wiring diagrams.
- A pre-flight checklist covering field assembly, motor installation, recovery preparation, launcher installation and system arming.
UKRA says the report is also forwarded to the Chair of the STC as a courtesy, and that the STC examines it and completes a risk assessment.
What is on the data capture form?
UKRA's Level 3 Data Capture page lists what to give before the flight: the rocket's name, whether it is a kit or scratch built, length, diameters, weight without the motor, an avionics description, how recovery is actuated, motor type, method of ignition and launcher type (rod, rail or tower). It also asks for the stability margin, calculated altitude and calculated velocity, each with how it was calculated, plus an estimated maximum recovery range, a pre-flight assembly plan with any on-site tests, and the launch sequence.
A second part is filled in after the flight: corrective actions and anomalies during assembly and launch, the flight profile and any anomalies in it, and a post-flight assessment. UKRA says this part is just as important as the rest. The two STC signatories finish the form with their comments and a yes or no on approval.
What does the reviewer check?
UKRA's Level 3 Review Checklist is the list an STC member uses to decide whether to sign off. It covers the airframe, recovery system, avionics, motor, launcher, performance calculations and operations. For each area it asks for the most probable faults, the safety effect of a failure and any design changes. A few examples from the page:
- Avionics: whether they are commercial or a unique design, whether the inhibits can be reached from outside the vehicle, whether there are safing and arming indicators, and whether any systems are redundant.
- Motor: whether the motors are HSE or UKRA certified, and whether they are experimental or tested.
- Performance: how the calculations were done, which software was used, and whether they should be run independently.
- Operations: whether the checklist covers each operation and flags the hazardous ones.
Who signs it off?
The Procedure page says the flyer needs two different STC signatures: one from the project advisor and one from another STC member after a full inspection of the assembled vehicle without the motor. Once both are given the project is flight ready. One signatory must be at the launch to witness the flight with the site RSO, who must also be Level 3 certified. The STC can refuse sign-off at any time if the flight cannot be made safely. The flyer must be a UKRA member in good standing with at least third party liability insurance for the flight.
Do the UKRA pages agree?
Not entirely, so check with UKRA before you start. The main Level 3 page describes a mentor, a Project Report and a flight test signed off by two certified RSOs, one of them Level 3. The Procedure page describes two STC signatures and a report two months before launch. We have not tried to reconcile them. UKRA also says to register through the Members Portal and talk to the STC before construction begins.
Questions
What is in a UKRA Level 3 project report?
A completed Pre-Flight Data Capture form, drawings, a parts list, a motor assembly diagram, recovery electronics schematics and a pre-flight checklist, says UKRA.
When should the report be sent?
UKRA's Procedure page says two months before the intended launch, to your project advisor on the STC.
Who reviews it?
Members of UKRA's Safety and Technical Committee, who also complete a risk assessment, according to UKRA.
Do I need a Level 3 report for a model rocket?
No. Level 3 applies to M class and above, over 5120 Ns combined impulse. Check the UKRA Safety Code for the rules that apply to your rocket.
Has NOVTAR Solace flown?
No. NOVTAR Solace is in design and has not flown, and it is not a Level 3 project.
Next steps
- UKRA Level 2 and Level 3 certification explained
- UKRA Level 1 high power certification explained
- Model rocket electronics, TVC and GPS under UKRA rules
Read the code before you fly: UKRA Safety Code. Sources: UKRA, Level 3 Procedure, Level 3 Data Capture and Level 3 Review Checklist (read 25 November 2026).